HTS was chosen as the best overall life cycle solution, providing reliable, sustainable, cost-effective equipment. For the three buildings renovated in this project, two 600 ton Daikin Pathfinder chillers, and 13 Daikin Vision air handling units (totaling 101,470 CFM) with Q-Pac Fans and ECM motors for efficiency were installed. The Vision AHU’s had to be shipped in small sections & fit in the existing footprint, and we worked hard to make sure the project ran smoothly.
UIW School of Osteopathic Medicine
- Owner University of Incarnate Word
- ArchitectMcChosesney/Blanco Architecture
- General ContractorJoeris General Contracting
- Mechanical ContractorComfort Air
- MEP EngineerMS2 Engineering